Salesforce Marketing Cloud migration · Inventory, DE mapping & cutover

Your Marketing Cloud exit starts with the contract, not the first journey.

SFMC bills every contact until you delete it and keeps about six months of engagement history. Lock the notice date and the data export first, then rebuild. On this page
Northwind Health · SFMC exit plan
Toggle to change which work starts first. Same team, same 12 months (illustrative).
Order form & notice date
Archive Data Views monthly
Inventory & retire
DE mapping & build
IP warmup & parallel run
Cutover & decommission
M7 non-renewal notice deadlineM9 term ends
Notice deadlineMet in M1
Engagement historyArchived
Next SFMC termNone
Notice sent in month 1. History is archived every month, cutover lands in M8, and SFMC is gone before the term ends.
Why this breaks

SFMC migrations fail on the calendar and the data, not the tool swap.Four root causes show up in almost every enterprise exit we scope.

Most failed Marketing Cloud migrations started too late, not too slowly.

01

The contract sets the critical path

Billing counts contacts, and records stay billable until deleted. Unsubscribes still count (Redress Compliance, 2026). A missed non-renewal notice can lock in another term at current size.

02

The logic hides in code

Eligibility and personalization live in AMPscript Lookup calls, SSJS Script Activities and SQL Query Activities. None of it shows up in an asset count.

03

History expires and consent is scattered

Event Data Views keep about six months. Opt-outs sit in All Subscribers, BU unsubscribes, publication lists, suppression lists and Salesforce fields.

04

Reputation and sync don't transfer

New IPs start from zero with mailbox providers. Marketing Cloud Connect gets switched off before the new CRM sync is proven.

What good looks like

Benchmarks your CFO and your deliverability team will both accept.Timeline, warmup, sender health and the contract numbers, each with its source.

An email-focused SFMC exit takes 6–12 weeks. Multi-BU instances with 30+ journeys take 12–20.

MetricWeakAcceptableStrongSource
Enterprise SFMC migration timelineOver 20 weeks (global, multi-BU, no MVP scope)12–20 weeks (30+ journeys, complex data)6–12 weeks (under 30 journeys, email-focused)Rackwave, 2026
SFMC to HubSpot timelineOver 18 weeks12–18 weeks ("most")8–10 weeks (simpler instances)HubXpert, 2026
Dedicated IP warmupUnder 4 weeks, or sends skipped mid-ramp4–6 weeks of daily sendsHubSpot's 40-day automated ramp, no 7-day gapsSalesforce Ben, n.d.; HubSpot KB, 2026
Monthly volume vs. dedicated IPUnder 100K/month on a dedicated IP100K–250K/month: dedicated recommendedOver 250K/month: dedicated requiredSalesforce Help 000383515, 2026
Spam complaint rate0.30% or higherUnder 0.10%Under 0.08% during warmupRed Sift, 2026; Rackwave, 2026
Bounce rate during warmupOver 2%Under 2%Under 0.5% (practitioner estimate)Rackwave, 2026
Unsubscribe processingOver 2 daysWithin 2 daysReal-time, RFC 8058 one-clickRed Sift, 2026
Billable contacts inactive or unmailableOver 30%15–30% (median 22%)Under 15%Redress Compliance, 2026
Super message allowance vs. usageAbout 3x usageAbout 2x (typical)1.2x or less, with true-up rightsRedress Compliance, 2026
Renewal cut from right-sizing onlyUnder 15%15–30%26% medianRedress Compliance, 2026

Sources: Rackwave, "Migrating from SFMC to Braze," May 2026 (scenario bands, warmup thresholds). HubXpert SFMC-to-HubSpot page, 2026 (agency estimate). Salesforce Ben, IP warming guide, undated; HubSpot Knowledge Base, "Connect a dedicated IP," Aug 2026. Salesforce Help 000383515, Dedicated and Shared IP use policy, accessed Oct 2026. Red Sift bulk sender requirements, Oct 2026. Redress Compliance, SFMC licensing and negotiation guides, Sept 2026 (advisor data from 25–45 accounts, not independently verified).

Where an SFMC invoice usually goes

Typical bill composition, advisor estimate (Redress Compliance, 2026). Bar widths use the midpoint of each range.

Base edition 30–45%Contact tier 20–35%Super messages 15–30%Add-ons & overage 10–20%

List context (Salesforce, Sept 2025): Engagement+ runs $2,000 (Pro), $5,500 (Corporate) and $30,000 (Enterprise) per org per month, billed annually.

The step-by-step playbook

Ten steps from order form to a decommissioned Marketing Cloud.Phased by business unit, with suppression loaded before anything sends.

Contract and data first, rebuild second, cutover by program, decommission last.

Wk 0–2Contract & platformSteps 1–2
Wk 1–5Inventory & dataSteps 3–5
Wk 3–10Build & translateSteps 6–8
Wk 6–14DeliverabilityStep 9
Wk 10–16+CutoverStep 10
01
Week 0 · Contract

Baseline the contract and start the clock

What

Term end, auto-renew and notice clause, contracted contacts, super messages, add-on SKUs, overage rate, plus 12 months of usage.

Why

The CFO needs a cost baseline. The notice date sets the plan's critical path, not the build.

How

Pull the order form, then the usage reports per Business Unit.

  • Contacts from Account Usage reports plus _Subscribers counts per BU; super messages from the Account Send Summary or Digital Wallet.
  • Size the dead weight: a 12-month no-open, no-click, held, bounced and unsubscribed segment. Redress puts the median at 22% of billable contacts.
  • Salesforce's Q4 (Nov–Jan) is when account teams have the most room to negotiate (Redress, 2026). If cutover can't finish before term end, negotiate a short bridge instead of auto-renewing.
  • Check for stranded SKUs such as Social Studio, retired Nov 18, 2024.
02
Weeks 0–2 · Decision

Pick the destination with a scored rubric

What

Choose the target before inventorying. The choice changes every mapping that follows.

Why

A record-centric B2B platform and an event-centric B2C platform need different data models.

How

Score each option on data fit, CRM, channels, volume, dev capacity, 3-year TCO and exit risk.

  • 3-year TCO: license, add-ons, implementation, parallel-run months and the headcount now spent on AMPscript and SQL.
  • Score "stay and right-size" as a real option. Use the MAP selection guide rubric so finance sees the same criteria for every option.
HubSpot Marketing Hub

B2B teams that want self-serve workflows without developers and a lower bill.

Account Engagement

Salesforce stays the system of record. A different product, so still a full migration.

Braze, Iterable, MoEngage

App, push and SMS at scale with a warehouse-first data team.

Stay and right-size

Deep Data Cloud use. Right-sizing cuts 15–30% (Redress), the bar a migration must beat.

03
Weeks 1–3 · Inventory

Inventory every asset in every Business Unit

What

Catalog every DE, journey, automation, template, CloudPage, query and script. Tag each migrate, rebuild or retire.

Why

Hidden code is the biggest scope risk. Retiring dead assets is the biggest savings.

How

Query the system Data Views per BU, then export metadata through the APIs.

  • Journeys: query _Journey and _JourneyActivity. Automations: _AutomationInstance and _AutomationActivityInstance for last run. Sends: _Job.
  • Run each query in every child BU. These views return data only for the BU you query (Dabrowski).
  • Bulk export metadata as JSON through the APIs (/interaction/v1/interactions, /asset/v1/content/assets) or SFMC DevTools (mcdev).
  • Retirement rule: no send or entry in 6 months means retire, unless Legal requires it.
04
Weeks 2–4 · Data model

Map each Data Extension to a target structure

What

Give every kept DE one disposition: property, custom object, HubDB, warehouse, or drop.

Why

This is where data loss and object-limit blowouts happen.

How

Classify by cardinality to the subscriber and by whether a person acts on each record.

  • Sendable master DE and All Subscribers become Contacts. Create sfmc_subscriber_key as a unique property (hasUniqueValue=true) so imports and associations can key on it.
  • SFMC stores dates in CST/CDT; convert to UTC in the transform.
  • Custom object limits on standard Enterprise are 10 definitions and 1M records, with more on flexible pricing (MarTech Devs, 2026). Extra packs cost $500/month.
SFMC Data Extension typeHubSpot targetRule of thumb
Sendable master / All SubscribersContacts, keyed on sfmc_subscriber_keyEmail maps to email; Salesforce IDs come through the connector
1:1 attribute DEsContact propertiesPicklists become enumerations; dates become date properties
1:N DEs people act onCustom objects with association labelsSubscriptions, policies, registrations, orders
High-volume event DEsWarehouse, plus rollup propertiesSend last_purchase_date, lifetime_orders, not rows
Lookup / reference DEsHubDB tablesStore lists and catalogs used by AMPscript Lookup
Synchronized DEs (MC Connect)Don't migrateThe HubSpot–Salesforce integration recreates them
05
Weeks 2–5 · Data

Extract history, consent and suppression first

What

Archive engagement history and build one master suppression file before the new platform sends anything.

Why

Event Data Views keep about six months, and _ReconcilableDispositionView keeps seven days.

How

Query Activities into archive DEs, then Data Extract and File Transfer to SFTP.

  • One Query Activity per view: _Sent, _Open, _Click, _Bounce, _Complaint, _Unsubscribe. Use LEFT(SMTPBounceReason, 4000) to fit the DE field limit.
  • Suppression master: union _Subscribers (unsubscribed, held, bounced), _BusinessUnitUnsubscribes per BU, _ListSubscribers, auto-suppression lists and Salesforce HasOptedOutOfEmail.
  • Load opt-outs as opted out of the matching subscription types and hard bounces into an always-excluded list. Sign off the reconciled counts.
06
Weeks 3–7 · Build

Replace Marketing Cloud Connect with a designed CRM sync

What

Swap MC Connect for the HubSpot–Salesforce integration.

Why

Lead routing, attribution and sales visibility all ride on the sync.

How

Dedicated integration user, one inclusion list, explicit field-direction rules.

  • Dedicated integration user with API Enabled and Modify All on synced objects (HubSpot KB, 2026). Turn Smart Transfer off first to avoid duplicates.
  • Inclusion list: one active list, no nesting (for example, "Sync-Ready = true OR has Salesforce ID"). Keep sync-deletes off until reviewed.
  • Model the Salesforce API budget before the backfill: each contact sync can use up to 4 API calls per record, and sync runs every 10–15 minutes.
  • Mirror publication lists as subscription types. Map each BU to a HubSpot brand, or a separate portal if data must be legally isolated.
07
Weeks 4–10 · Translate

Rebuild journeys as workflows, MVP first

What

Move the top 5–10 journeys by revenue or compliance, prove them live, then batch the rest.

Why

Entry sources and DE re-evaluation behave differently in the target. One-for-one ports carry the mess across.

How

Translate element by element, and redesign the journeys that no longer match how you sell.

  • SQL Query Activities become active lists, "set property" actions or warehouse jobs. SSJS becomes Data Hub custom code or a serverless function.
  • Use Stop, not Pause, on retired journeys at cutover so nothing re-enters from a backlog.
SFMC elementHubSpotAccount EngagementBraze
Entry Source: Data ExtensionEnrollment trigger: list or property filterEngagement Studio list entryScheduled-audience Canvas
Entry Source: API EventCustom event or webhook trigger (Data Hub)Flow or APIAPI-triggered Canvas
Decision / Engagement SplitIf/then branch; branch on open or clickRule branch; email listenerAudience and Action Paths
Wait by Duration / Until DateDelay; delay until date propertyWait stepDelay step
Goal / Exit criteriaGoal criteria and unenrollmentExit rulesExit criteria
Triggered / Transactional SendWorkflow email; transactional single-send APIOperational emailAPI-triggered campaign
AMPscriptHubL tokens, smart content, HubDBMerge fields, Dynamic ContentLiquid, Connected Content
08
Weeks 4–10 · Content

Convert templates and personalization code

What

Rebuild Content Builder emails, templates and CloudPages, and convert the scripting.

Why

AMPscript lookups, nested conditionals and date logic are the most underestimated work (Rackwave, 2026).

How

Token-by-token conversion, then render and data tests on seeded contacts.

  • %%=v(@firstname)=%% becomes {{ contact.firstname }}. IF/ELSEIF becomes HubL conditionals or smart content rules by list or lifecycle stage.
  • Lookup and LookupRows against reference DEs become HubDB queries in HubL. If you plan to render custom object records in email, confirm your tier supports it before designing around it.
  • CloudPages become landing pages and forms; the preference center becomes the subscription preferences page.
  • QA renders in Gmail, Outlook, Apple Mail and mobile against 10+ seeded edge-case contacts.
09
Weeks 6–14 · Deliverability

Authenticate domains and warm the new IPs

What

Set up DNS and ramp the new sending infrastructure while SFMC still carries most volume.

Why

Reputation doesn't move with you. Gmail moved from temporary 421 deferrals to permanent 550 rejections in Nov 2025 (Red Sift).

How

Volume-based IP choice, engagement-tiered audiences, daily monitoring with stop rules.

  • Use Salesforce's own thresholds as a starting point: dedicated IP required above 250K/month, recommended at 100K–250K, shared pool below that.
  • HubSpot dedicated IP: Pro or Enterprise plus the add-on, then A, MX (priority 0), SPF and DKIM records. The 40-day ramp pauses after 7 days without sends.
  • DMARC at p=none with rua reporting at minimum, aligned with the From domain.
  • Warmup audiences: 30-day engaged in week 1, then 60-day, 90-day, then all active. Leave contacts inactive 9+ months out of the migration (MoEngage, 2026).
  • Watch Google Postmaster Tools, Yahoo CFL and Microsoft SNDS daily. Stop the ramp above 0.1% complaints or 2% bounces. Our email deliverability audit covers this setup.
10
Weeks 10–16+ · Cutover

Run in parallel, cut over by program, then decommission

What

Migrate by use case or BU, give each a cutover date, then shut SFMC down.

Why

Big-bang cutover is the top failure mode in vendor guides, and early shutdown removes the rollback path.

How

A migration register with one row and one owner per program.

  • Register columns: owner platform, activation date, SFMC stop date, audience, success criteria, rollback.
  • T-14 days: freeze SFMC changes. T-1: final delta of new subscribers, unsubs and bounces through a Data Extract and a HubSpot import with marketableContactImport set on purpose.
  • Day 0: stop journeys and triggered sends, activate workflows, repoint forms. Day +30: reconcile counts and compare per-ISP KPIs to the SFMC baseline.
  • Decommission: export final archives, run Contact Delete in Contact Builder before the billing count date (it has a suppression window, so check your current setting), uninstall the MC Connect package, revoke API users and confirm non-renewal in writing.
Best practices

Twelve rules that keep the migration on budget and out of spam.

Most of these cost nothing. Skipping them turns a 12-week project into a second contract term.

  1. Start from the contract. Put the notice date and term end on the plan before scoping anything.
  2. Retire before you migrate. Anything idle for 6+ months is retired by default.
  3. Load suppression first and reconcile it before any record that can receive mail.
  4. Archive Data Views monthly from the day you decide. Every month of delay loses a month of history.
  5. Key everything on SubscriberKey with a unique sfmc_subscriber_key property.
  6. Use custom objects sparingly. Ask whether a person acts on individual records. If not, use a rollup or the warehouse.
  7. Set marketing contact status on purpose. Consented, engaged contacts only; it drives HubSpot billing.
  8. Ship MVP journeys first. The top 5–10 by revenue or compliance, proven live.
  9. Never let warmup sends pause. Calendar them like payroll; 7 idle days pauses HubSpot's ramp.
  10. One owner per program during the parallel run, so no one gets the same email twice.
  11. Design the CRM sync. One inclusion list, explicit field direction, API budget modeled before backfill.
  12. Measure against your own baseline. 90 days of SFMC per-ISP rates, not industry averages; Apple MPP inflates opens.
Common mistakes

Eight migration mistakes and what each one costs.

The expensive ones are calendar mistakes. The painful ones are data and deliverability mistakes.

Missing the non-renewal notice date

The contract renews while the team is still mapping DEs.

Cost: another term at current size. On a $500K/yr contract, $500K before any savings (illustrative).

Not exporting Data Views before term end

Event history older than about six months is already gone.

Cost: no 12-month engagement segments for warmup audiences, permanently.

Sending before suppression is loaded

Unsubscribed contacts get mail from the new platform.

Cost: CAN-SPAM and GDPR exposure; over 0.3% complaints, Gmail rejects mail.

Every DE becomes a custom object

The object model copies SFMC's sprawl.

Cost: the 10-definition, 1M-record cap gone, then $500/month per extra pack.

Skipping or pausing IP warmup

Full volume on a cold IP, or a gap mid-ramp.

Cost: throttling, spam placement and a reset ramp; revenue email underperforms for weeks.

Removing MC Connect before the new sync is proven

Lead routing and tracking write-back stop together.

Cost: broken attribution, so the first CFO report after cutover is wrong.

Lift-and-shift of every journey and AMPscript block

Stale journeys get rebuilt alongside live ones.

Cost: 12 weeks becomes 20+ (Rackwave bands), and the old complexity comes along.

Decommissioning before every program runs cleanly

SFMC goes dark with defects still open.

Cost: no rollback path, so any defect becomes an outage.
CFO calculator

Enter your instance. Get the contract math and a realistic timeline.Billable-contact cleanup, right-sizing range, dedicated IP need and weeks to cutover.

Every output uses a sourced benchmark or a labeled assumption. Your order form governs the real numbers.

1,200,000
22%
Default is Redress's 22% median. Use your 12-month no-open, no-click, held and bounced segment.
$450,000
45
3
1,500,000
9
Your notice deadline comes earlier. Check the order form.
Billable contacts to delete264,000Contacts × inactive share. They bill until deleted, even if unsubscribed.
Contact-tier spend on them$27,225 / yrAssumes contact tier = 27.5% of the bill (Redress range midpoint), priced linearly.
Right-size-only benchmark$68K–$135K15–30% of the contract (Redress). The "stay" number a migration must beat.
Dedicated IPRequiredOver 250K/month (Salesforce policy). 1 IP at ~2M/day capacity.
Estimated timeline12–20 wks30+ journeys or multiple BUs (Rackwave bands).
Contract clockFits39 weeks to term end vs. 20 weeks at the top of the band.
Plan at the top of your band

Missing the notice date commits another term: $450,000 at today's size.

Wave 1: your top 10 journeys. The other 35 get retired or batched after.

Phase split follows the 10-step playbook above. Warmup uses HubSpot's 40-day ramp when a dedicated IP applies. Planning figure for 20+ week bands: 24 weeks.

Sources: Redress Compliance SFMC licensing and negotiation guides (Sept 2026; advisor data); Salesforce Help 000383515 dedicated IP policy (accessed Oct 2026); Rackwave SFMC migration scenario bands (May 2026); HubSpot KB on dedicated IP warmup (Aug 2026). For the full cost model, see CRM migration cost and timeline.

Copyable cutover kit

Inventory columns, DE mapping spec, suppression query and cutover checklist.

Paste it into a sheet or your project tool. One kit covers the inventory through decommission.

sfmc-migration-cutover-kit.txt
=== A. SFMC ASSET INVENTORY (one row per asset, every Business Unit) ===
BU (MID) | Asset type | Name / external key | Folder path | Owner | Last modified
Last run / send / entry (_Journey, _AutomationInstance, _Job) | Volume (90 days)
Depends on (DEs, automations) | Contains code? (AMPscript / SSJS / SQL, complexity 1-3)
Sendable? (Send Relationship) | PII / consent relevance
Disposition: MIGRATE | REBUILD | RETIRE | ARCHIVE ONLY
Target object or workflow | Effort S/M/L | QA sign-off
Rule: no send or entry in 6 months = RETIRE, unless Legal requires it.

=== B. DATA EXTENSION -> OBJECT MAPPING SPEC (one row per field) ===
Source DE | Field | SFMC type / length / nullable / PK | Sample value
Cardinality to subscriber (1:1 or 1:N)
Target: Contact prop | Company prop | Custom object prop | HubDB | Warehouse | Drop
Target internal name | Target type (string / enumeration / number / date / datetime / boolean)
Transform (CST/CDT -> UTC, picklist map) | Unique ID? | Association label
Sync direction to Salesforce | Owner | Validation query

Disposition rules:
- Sendable master / All Subscribers -> Contacts, key = sfmc_subscriber_key (unique)
- 1:1 attribute DE -> contact properties
- 1:N DE a person acts on -> custom object + association label
- High-volume events -> warehouse + rollup properties
- Lookup / reference DE -> HubDB table
- Synchronized DE (MC Connect) -> do not migrate

=== C. SUPPRESSION MASTER (Automation Studio Query Activity, run per BU) ===
SELECT s.SubscriberKey, 'all_subscribers_' + s.Status AS Source
FROM _Subscribers s
WHERE s.Status IN ('unsubscribed','held','bounced')
UNION
SELECT b.SubscriberKey, 'bu_unsubscribe' AS Source
FROM _BusinessUnitUnsubscribes b
UNION
SELECT l.SubscriberKey, 'list_unsubscribe' AS Source
FROM _ListSubscribers l
WHERE l.Status = 'unsubscribed'
Then add: auto-suppression lists + Salesforce HasOptedOutOfEmail = true.
Load order: opt-outs and hard bounces BEFORE any mailable record.
Reconcile: source count = target count, signed off by the owner.

=== D. HISTORY ARCHIVE (one Query Activity per view, monthly) ===
_Sent, _Open, _Click, _Bounce, _Complaint, _Unsubscribe -> archive DEs
Bounce: use LEFT(SMTPBounceReason, 4000) to fit the DE field.
Export: Data Extract + File Transfer to SFTP -> warehouse.

=== E. CUTOVER CHECKLIST ===
T-30  [ ] DNS verified: A, MX (priority 0), SPF, DKIM, DMARC (p=none + rua minimum)
      [ ] Inclusion list built (one active list, no nesting)
      [ ] Field mappings and sync direction signed off
      [ ] Suppression master reconciled
T-14  [ ] SFMC change freeze
      [ ] MVP workflows QA'd in test mode
      [ ] Seed-list renders passed (Gmail, Outlook, Apple Mail, mobile)
T-1   [ ] Delta export/import: new subscribers, unsubs, bounces
      [ ] Final Data View archive
Day 0 [ ] Stop SFMC journeys and triggered sends (Stop, not Pause)
      [ ] Activate workflows; repoint forms and APIs
      [ ] Monitor Postmaster Tools hourly
Day+7 [ ] Reconcile contacts, opt-outs, custom object records, associations
      [ ] Compare per-ISP delivered / bounce / complaint to SFMC baseline
Day+30[ ] Decommission review
      [ ] Contact Delete in SFMC (check suppression window setting)
      [ ] Uninstall MC Connect package; revoke API users
      [ ] Confirm non-renewal in writing

=== F. WARMUP GATES (daily) ===
Week 1: engaged 30 days | Week 2: 60 days | Week 3: 90 days | Week 4+: all active
Stop the ramp if: complaints > 0.1% (hard stop 0.3%) or bounces > 2%
No weekend sends. No gap over 7 days on HubSpot's ramp.
Volumes per ISP: illustrative, calibrate to your daily volume.

=== G. CFO ONE-PAGER (3-year view) ===
Current: SFMC contract + SI/dev retainers + internal FTE time on AMPscript/SQL
Target:  license tier + add-ons (dedicated IP, transactional, custom objects)
         + migration project + parallel-run overlap months
Compare: 3-year TCO, payback month, risk register, notice date
FAQ

What marketing ops leaders ask before they leave Marketing Cloud.

Direct answers to the questions that come up in the first CFO meeting.

Can an enterprise Marketing Cloud migration be done without breaking sends?

Yes. Enterprise ones share a pattern: multiple BUs, dozens of journeys, AMPscript and SQL, and MC Connect feeding Salesforce. The ones that go well run phased by BU, load suppression first and cut over before the notice date. The method is close to our Marketo to HubSpot migration, with more custom code.

What will my CFO want to see, and what numbers do I bring?

A 3-year cost comparison, the notice date and what missing it costs, and the revenue risk from deliverability or lost consent. Bring the order form, 12 months of usage and your inactive segment size; the calculator above drafts the rest.

How long does an SFMC migration actually take?

An email-focused instance with under 30 journeys takes 6–12 weeks. 30+ journeys, complex data or several integrations take 12–20. Global multi-BU programs without MVP scoping run past 20 (Rackwave, 2026). The IP warmup alone takes about 40 days on HubSpot.

If we move, will we land in spam?

Not if you warm up properly: authenticate SPF, DKIM and DMARC, start with your most engaged contacts, send daily, and stop above 0.1% complaints or 2% bounces. SFMC carries the bulk until the new IPs are warm.

HubSpot, Account Engagement, a B2C platform, or just renegotiate?

HubSpot for B2B teams that want self-serve automation and a lower bill. Account Engagement if Salesforce is permanent and IT wants to stay in that contract; see our Pardot to HubSpot guide for how the two compare in practice. Braze or Iterable for app-heavy B2C. Renegotiate if right-sizing's typical 15–30% cut meets the CFO's target.

What happens to our AMPscript and Data Extensions?

Tokens become HubL personalization tokens and reference-DE lookups become HubDB queries. Each DE gets one disposition: property, custom object, HubDB, warehouse or retire. Synchronized DEs aren't migrated; the new CRM sync recreates them.

How JayOh does it

Contract first, then a re-architected cutover your CFO can sign.A consultant who owns the outcome, developers who ship in weekly sprints.

Migrations fail on data mapping, automation rebuild and adoption, not the tool swap. We migrate you into a system designed for how you sell now, not a copy of the old instance.

  • Week 0 is the order form. Notice date, contact tier, super messages and stranded SKUs mapped to a 3-year TCO and payback month.
  • Platform-neutral. As a HubSpot and Salesforce partner, we'll say so when Account Engagement, a B2C platform or a right-sized renewal wins.
  • Reconciled data, every load. Suppression first, Data Views archived from day one, SubscriberKey kept, counts signed off.
  • Deliverability in the plan. Domain authentication, engagement-tiered warmup and daily Postmaster checks are scoped tasks, not afterthoughts.
4→2platforms consolidated in 90 days (post-merger case study)
90%reduction in data errors
28%lift in forecast accuracy
$2.2Mpipeline in 90 days once the new stack was live

Weeks 0–2: contract and inventory

Your consultant maps the order form, scores the destination and runs the per-BU inventory.

Weeks 3–10: build in sprints

Developers build the data model, CRM sync, MVP workflows and templates in weekly sprints while the warmup ramps in parallel.

Cutover: one owner, one register

The consultant runs the migration register, signs off each reconciliation and only decommissions SFMC after the last program runs cleanly.

We'll map the notice date, the billable-contact cleanup and a 3-year TCO your CFO can sign.